Remember me from last week? We're back and still going at it!
Logan and Preston removed all the hood doors, radiator fan grill, some large exterior pieces of piping, and other miscellaneous awkwardly constructed pieces in preparation for sandblasting.
Matt S, Zebulon, and Shea continued needle-scaling the frame and trucks of the engine. Logan started needlescaling the long hood.
Not pictured, Tony and Joey continued working on the top deck of the engine, working on cleaning up the valve train assemblies.
Ben finished up the battery box on the engineer side (I lied last week when I said we were done, but we were really close). He also finished the fireman's side window and installed the window tracks.
Thanks to Kyle Smith at Smith Dustless Sandblasting LLC, we were able to get many important pieces sandblasted. This was a huge help in getting us closer to the painting stage.
Matt, Logan, and Alex primed the sandblasted pieces into the evening hours.
Also another shout out to Tony who after putting in a solid amount of work on Tuesday evening, showed up again for most of Sunday to keep working on the top deck of the engine.
Donations are so important to this project. We're still short on funding to finish off the wheelwork and painting the engine.
Please consider donating to the project at either:
https://www.paypal.com/donate/?hosted_button_id=MGT9MM7VLL2XU
or
https://rmne.membershiptoolkit.com/packet/t86847589
Want to get involved? Check out https://www.rmne.org/volunteer 🤝🚂
Thank you all for your continued support!